GAS INSULATED SUBSTATIONS  (GIS)

1/9

ALIVERI GIS

 

Completion period: 2012–2013

Contractor: METKA

Project Owner: PPC  

Location: Aliveri, Evoia

Description of works: Electrical installation of the 150/20 kV gas insulated substation.

1/5

PALAIO FALIRO GIS

 

Completion period: 2003

Contractor: ALSTOM HELLAS

Project Owner: PPC  

Location: Palaio Faliro Attica

Description of works: Electrical installation of the 150/20 kV gas insulated substation.

 

KORIDALLOS GIS

Completion period: 2002

Contractor: AREVA

Project Owner: PPC  

Location: Korydallos-Athens

Description of works: Electrical installation of the 150/20 kV gas insulated substation.

 