top of page

PROJECTS IN PROGRESS

Here you will find projects that are currently being implemented by ELECTROTECHNIKI S.A.

DESFA OF

CENTRAL GREECE

​Completion period: September 2024 – In progress

Project Owner: DESFA

Contractor: TERNA S.A. - Damco Energy S.A.

Location: Ampelia, Municipality of Farsala

Description of works: Complete electrical installation and erection of instruments of the natural gas compression station

BOOSTER

NEA MESIMVRIA

Completion period: January 2026 – In progress

Project owner: DESFA S.A.

Contractor: TERNA – Damco Energy SA

Location: Nea Mesimvria, Thessaloniki

Description of work: Complete electrical erection and instrumentation installation works in Booster Compression Station for TAP

SUBSTATION - FOLEGANDROS

Completion period: September 2025 – In progress

Project owner: ADMIE S.A. – HEDNO S.A.

Contractor: TERNA S.A.

Location: Folegandros

Description of works: Complete electrical construction of a 150 kV GIS substation within the framework of the 4th phase of the Cyclades interconnection

450 MW PV PARK

INTERCONNECTION

Completion period: February 2025 – In progress

Project owner: AMYNTEO SOLAR PARK NINE SINGLE MEMBER SA

Contractor: TERNA S.A.

Location: P.P.C. Amyntaion Mine

Description of works: Electrical works for the interconnection of medium voltage cables of a PV park with a total nominal power of 450 MW

 

HERON - THEBES

Completion period: February 2026 – In progress

Project owner: SUSTAINABLE ENERGY SOLUTIONS SA

Contractor: TERNA S.A.

Location: Thebes

Description of works: Complete electrical construction of a Battery Energy Storage System (BESS) at the HERON facilities in Thebes

550 MW PV PARK

INTERCONNECTION

Completion period: July 2025 – In progress

Project owner: PHOEBE ENERGY LLC.

Contractor: TERNA S.A.

Location: P.P.C. Ptolemaida Mine

Description of work: Electrical works for the interconnection of medium voltage cables of a PV park with a total nominal power of 550 MW with the Kardia steam power station

 

PV PARK 450 MW

Completion period: June 2025 – In progress

Project owner: AMYNTEO SOLAR PARK NINE SINGLE MEMBER SA

Contractor: TERNA S.A.

Location: P.P.C. Amyntaion Mine

Description of works: Complete electrical construction of a PV park with a total nominal power of 450 MW

 

PV PARK 550 MW

Completion period: February 2025 – In progress

Project owner: PHOEBE ENERGY LLC.

Contractor: TERNA S.A.

Location: P.P.C. Ptolemaida Mine

Description of work: Complete electrical construction of a PV park with a total nominal power of 550 MW

WIND FARM - 

LOUZES NAFPAKTOS

Completion period: February 2026 – In progress

Project owner: PPC S.A.

Contractor: TERNA S.A.

Location: Nafpaktos

Description of work: Replacement of main wind farm transformer at Louzes location

BOEHRINGER

INGELHEIM

Completion period: September 2016 - In progress

Project Owner: BOEHRINGER INGELHEIM

Contractor: TERNA SA

Location: Koropi, Attica

Description of works: Electrical works for the extension – upgrade of Koropi pharmaceutical industry of Boehringer Ingelheim Hellas.

bottom of page