top of page

PROJECTS IN PROGRESS

Here you will find projects that are currently being implemented by ELECTROTECHNIKI S.A.

KLEITOS SUBSTATION

Completion period: September 2004 – In progress.

Project Owner: PPC RENEWABLES.

Contractor: TERNA S.A.

Location: South Field Coal Mine in the Municipality of Kozani.

Description of works: Complete electrical installation of a 33/150 kV substation for the interconnection of P/V plants with total rated capacity 550 MW.

STEAM POWER PLANT LINOPERAMATA - CRETE

Completion period: April 2024 – In progress

Project Owner: P.P.C.

Contractor: TERNA S.A.

Location: Linoperamata, Crete, Greece

Description of works: Removal of current electrical equipment from Thiva and electrical installation of three power plant units 130 MW at Linoperamata Power Station

 

ARIADNE

 

Completion period: August 2023 – In progress

Project Owner: ARIADNE INTERCONNECTION S.A.

Contractor: TERNA S.A.

Location: Aspropyrgos, Attica

Description of works: Electrical installation of main equipment in Koumoundourou Converter Station for the electrical (DC) interconnection between Attica and Crete (2x500 MW).

 

COMBINED CYCLE POWER PLANT IN KOMOTINI

 

Completion period: February 2023 – In progress

Project Owner: THERMOILEKTRIKI KOMOTINIS

Contractor: TERNA S.A.

Location: Industrial area of Komotini.

Description of works: Electrical installation, testing, commissioning and start up of the new gas combined cycle unit 876.6 MW.

 

STEAM POWER PLANT 

PTOLEMAIDA V

 

Completion period: December 2017 - In progress

Project Owner: PPC

Contractor: TERNA SA

Location: Ptolemaida

Description of works: Electrical installation in main facilities (boiler, turbine, main electrical building), testing, commissioning and start-up of the new steam power plant 660 MW. Electrical works in building KT4 & KT1A.

 

BOEHRINGER

INGELHEIM

 

Completion period: September 2016 - In progress

Project Owner: BOEHRINGER INGELHEIM

Contractor: TERNA SA

Location: Koropi, Attica

Description of works: Electrical works for the extension – upgrade of Koropi pharmaceutical industry of Boehringer Ingelheim Hellas.

bottom of page