DIESEL GENERATORS
RHODES
Completion period: 2016-2018
Project Owner: PPC
Contractor: TERNA SA
Location: South Rhodes
Description of works: Electrical installation of seven diesel generators of total capacity 115 MW. Installation of electrical equipment, cable trays, cables, lighting, earthing & grounding. Commissioning & start up.
APS (AUTONOMOUS PRODUCTION STATION) OF MYKONOS
Completion period: June 2009-September 2009
Project Owner: PPC
Contractor: SOLERGON
Location: Mykonos
Description of works: Electrical installation of 3 diesel engines 5.8 MW each.
E/S AEGEAN ISLANDS
Completion period: 2008-2012
Project Owner: PPC
Contractor: SOLERGON
Location: Aegean Islands
Description of works: Electrical installation of sixty one diesel generators of total capacity 61 MW in the following islands:
-
Syros
-
Lesvos
-
Chios
-
Symi
-
Patmos
-
Sifnos
-
Rhodes
-
Mykonos
-
Κύθνος
-
Samos
-
Skyros
-
Astypalea
OLYMPIC GAMES 2004
Completion period: 2004
Project Owner: ATHENS 2004
Contractor: J / V METKA-GE
Location: Athens
Description of works: Installation and operation of emergency diesel generators for supporting of all the Olympic and Paralympics venues during the Olympic Games.
APS (AUTONOMOUS PRODUCTION STATION) OF SORONIS
Completion period: 1998
Contractor: PPC
Location: Soronis, Rhodes
Description of works: Electrical installation, commissioning and start up of new diesel generator.