top of page
GAS INSULATED SUBSTATIONS  (GIS)

SUBSTATION - FOLEGANDROS​

Completion period: September 2025 – In progress

Project owner: ADMIE S.A. – HEDNO S.A.

Contractor: TERNA S.A.

Location: Folegandros

Description of works: Complete electrical construction of a 150 kV GIS substation within the framework of the 4th phase of the Cyclades interconnection


ALIVERI GIS

Completion period: 2012–2013

Project Owner: PPC  

Contractor: METKA

Location: Aliveri, Evoia

Description of works: Electrical installation of the 150/20 kV gas insulated substation.


PALAIO FALIRO GIS

Completion period: 2003

Project Owner: PPC  

Contractor: ALSTOM HELLAS

Location: Palaio Faliro Attica

Description of works: Electrical installation of the 150/20 kV gas insulated substation.


KORIDALLOS GIS

Completion period: 2002

Project Owner: PPC  

Contractor: AREVA

Location: Korydallos-Athens

Description of works: Electrical installation of the 150/20 kV gas insulated substation.

bottom of page