CRANES STS
(SHIP TO SHORE)

PIRAEUS PORT AUTHORITY S.A.

Completion period: 2013

Project Owner: PIRAEUS PORT AUTHORITY

Contractor: ROKAS CONSTRUCTIONS SA

Location: Pier 1 port of Piraeus

Description of works: Electrical installation, testing and commissioning of three cranes.

TARTOUS SYRIA

Completion period: 2010

Project Owner: PIRAEUS PORT AUTHORITY (PPA)

Contractor: ROKAS CONSTRUCTIONS SA

Location: Piraeus Port

Description of works: Electrical installation, testing and commissioning of two cranes for the Tartous port in Syria.